Running your branches
Par levels: what they are and how to calculate them
Short answer
A par level is how much of a product a site should hold so it lasts until the next delivery, with a small buffer. The formula is par level = daily use × (days between deliveries + safety days). To order, count what is on the shelf and take it away from the par: order = par level − stock on hand.
Par level calculator
Enter what one branch uses of one product. The calculator gives the par level and how much to order after today’s count.
Par level
18 kg
Order now: 12 kg · daily use 2 kg
The par level formula, step by step
Find weekly use
Take the last four weeks and average them. If you count weekly, use = last count + deliveries in − this count.Turn it into daily use
Divide weekly use by 7, or by the number of days the site trades.Count the days between deliveries
If head office delivers every Monday, that is 7 days. Twice a week is about 3 or 4.Add safety stock
One to three days for most products. It covers a busy weekend, a late van or a miscount.Multiply
Par level = daily use × (days between deliveries + safety days).Order the gap
After the count, order par level − stock on hand. Never order a negative number: if you are above par, order nothing.
Worked examples
| Product | Weekly use | Delivery every | Safety | Par level | On hand | Order |
|---|---|---|---|---|---|---|
| Beef patties | 14 kg | 7 days | 2 days | 18 kg | 6 kg | 12 kg |
| Brioche buns | 21 boxes | 3 days | 1 day | 12 boxes | 5 boxes | 7 boxes |
| House sauce | 28 | 7 days | 3 days | 40 | 14 | 26 |
| Delivery bags | 10 packs | 7 days | 7 days | 20 packs | 12 packs | 8 packs |
Notice the delivery bags: packaging is cheap to hold and does not go off, so a full week of safety stock costs little and saves an emergency run to the cash and carry. Fresh bread is the opposite: a short gap between deliveries and one day of safety keeps waste down.
Par levels across more than one branch
Each branch needs its own par for each product. A city-centre site that trades lunch and late nights will use far more than a suburban site with the same menu. Head office then needs its own par too: enough central stock to cover every branch’s next deliveries plus the supplier’s lead time.
Head office par
Add up the weekly use of all branches, divide by 7, and multiply by the supplier’s lead time plus your safety days. If your butcher delivers in two days and you keep three days of safety, head office par for patties across four branches using 14 kg each is about 56 ÷ 7 × 5 = 40 kg.
Common mistakes
- Setting one par for every branch.
- Never updating pars after a menu change.
- Working out use from deliveries instead of counts, which hides waste.
- Ordering by eye on busy days, which makes the par meaningless.
In TradePack Supply
Set a par level per product for each branch. After a branch counts its stock, TradePack Supply suggests the next request from the par and the count, and the branch manager sends it with one tap. Head office is warned when central stock runs low. See how it works.
Questions people ask
What is a par level in a restaurant?
A par level is the amount of a product a site should have on the shelf after a delivery, so it lasts until the next delivery with a little spare. If the par for beef patties is 24 kg and the branch has 6 kg left, it orders 18 kg.
How do you calculate par levels?
Work out average daily use, multiply it by the number of days between deliveries, and add safety stock for a few extra days. Par level = daily use × (days between deliveries + safety days).
How much safety stock should a takeaway keep?
Most food businesses keep one to three days of safety stock. Use less for short shelf-life items such as fresh bread and dairy, and more for long-life items that are cheap to hold, such as packaging and sauces.
How often should par levels be reviewed?
Review them every month, and straight away when the menu changes, a promotion starts or the season turns. A par set in a quiet month will run short in a busy one.
What is the difference between a par level and a reorder point?
A par level is how much you want to hold after a delivery. A reorder point is the level at which you place the next order. Food businesses with fixed delivery days usually work with par levels, because they order on a schedule rather than when stock hits a number.